Ongoing Construction Update

Expansion of the North Ramp began in January 2018. It will re-open on or about April 1st. The North Ramp will be completed in September 2018 and will provide more than 400 parking stalls for customers and employees. 

Demolition of the Center Ramp will begin April 2nd, 2018. This will be an active construction site for more than one year. When complete in Fall 2019, this site will feature new apartment homes, new retail shops, and 100+ stalls of indoor customer parking all centered around a series of pedestrian ways and public plazas.

 

Market Street Construction Update

June 15, 2018

North Ramp Expansion

  • The third of four major concrete pours is being completed on the east side this Friday, June 15.
  • This work to be finished around 12:30 p.m.

Next week's construction activity:

Friday, June 22:

     
  • Work will begin at 4 a.m. to be finished around 12:30 p.m. Expect many concrete trucks on site that morning.
  • The orange route leading from the west stairwell will be closed during this time.
  • All clients and employees will be re-routed to use the ease stairway/purple route.
  • A & P will have staff on site to direct pedestrians to the east stairwell (purple).
  • Access to the post office will remain open.

Other work this week:

     
  • Crews will continue framing on the 4th level (west side).
  • Brick repair will be ongoing on ground level (south side).
  • Painting of interior decks, walls, and columns will continue (10 p.m. to 6 a.m.) when the ramp is not in use.
  • Painting to begin on exterior of existing structure (south side).
  • June 20-22 shoring from the east addition will be dismantled and transported off site. There will be one to two semi trucks daily.

Nolan Mains Construction Updates

  • The vibrations and loud banging are over at 50th & France.
  • June 15 is the last day for any loud noises related to installation of the shoring for the construction project.

Next week's construction activity:

  • Lagging and Tie Back anchor installation continues along the south edge of the site (50% completed).
  • Excavation and removal of soil continues through July (40% completed).
  • Concrete pumping for footing and foundation work will begin June 18. This work will be staged onsite.
  • Tower Crane erection will occur June 25-28. Trucks will be staged onsite and will not require any road closure.

Parking Conditions:

Due to low ridership, the City will discontinue the employee shuttle service. The last day of service will be Friday, June 15.  All riders have been notified of this change. Thank you to those who participated and stepped up to help create a better customer experience at 50th & France.

The City has created a Parking Map detailing Public Parking near 50th & France. Several public and employee parking options are available at 50th & France. Parking is also available on local streets as shown on the map. 
 
STAY INFORMED - Sign up for City Extra emails. This will give you information on any city emergency and road closure within Edina.

Schedule for Monthly Construction Updates
  
Construction Mitigation and Parking Management Plan, Dec. 2017

Valet Parking FAQ

Parking Map